On Thursday, April 1st, the City's contractor will begin setting up traffic control, which will close the west half of the 27th Street and Hall intersection. Traffic will be detoured using Augusta Lane. See detour map. Hall Street traffic will be carried through head-to-head in the east lanes of the intersection. See traffic control map.
Once the construction zone is isolated, the existing pavement will be removed, the subgrade will be stabilized with crushed concrete, and new pavement will be installed. The curb and gutter, sidewalk and ADA Ramp in the northwest corner of the intersection will be replaced as well. All this work will take about three weeks.
Once that phase of construction is complete, then Hall Street traffic will be moved to the west side of the intersection on the new pavement while work begins in the SE corner of the intersection and proceeds eastward down the south side of 27th Street.
All this information and more can be found on the project webpage at haysusa.com or by contacting the Office of Project Management at 785 628-7350.