Please be advised that on Friday, March 15, 2019, the City's contractor will begin installing concrete shoulders along the side of 8th Street east of Vine Street. During hours of construction activity (7:30 am to 5:00 pm) traffic will be restricted to east bound one-way only. After hours, the road will be restored to two-way traffic. The project is scheduled to be completed within two weeks (pending weather conditions).
Signs will be in place to direct the traveling public. The traveling public should use caution and if possible avoid this area.
The City of Hays regrets any inconvenience this may cause to the public. If there are any questions, please call the Office of Project Management at 628-7350 or the contractor, J-Corp, at 628-8101.